FG completes first phase rehabilitation of Third Mainland Bridge

FG completes first phase rehabilitation of Third Mainland Bridge

The Federal Government on Thursday announced the completion of the first phase rehabilitation of the Third Mainland Bridge and a planned 18 hours total closure of the bridge.

The Federal Controller of Works in Lagos, Olukayode Popoola said that the fixing of six expansion joints on the Oworonshoki bound carriageway had been completed.

Advertisement

Popoola said that debris would be cleared from the section and construction would move to the Island-bound carriageway, warranting a total closure of the bridge for 18 hours.

He said that the 18 hours closure would begin from midnight on Saturday through Sunday to move construction materials to the new portion and return to the partial closure before Monday morning.

Advertisement

He said by midnight of Sunday, the total closure would be removed and the partial closure would return, which gives priority for huge traffic in and out of the Island

”Work is to commence on the Island-bound lane of the bridge with the partial closure of Adekunle to Adeniji Adele Phase B.

“The repair work is to commence between 22nd of November, 2020 and 22nd of February, 2021 for duration of three months.